NOTE H – COMMITMENTS AND CONTINGENCIES Engineering, Procurement and Construction Contract On April 30, 2020, GCE Acquisitions entered into an Engineering, Procurement and Construction Agreement with a national engineering firm pursuant to which this firm agreed to provide services for the engineering, procurement, construction, (“EPC”) start-up and testing of the Bakersfield Biorefinery. The agreement, which was assigned by GCE Acquisitions to BKRF OCB, LLC, the borrower under the Senior Credit Facility, provides for this engineering firm to be paid on a cost-plus fee basis subject to a guaranteed maximum price of $201.4 million, subject to increase for approved change orders. As of May 17, 2021, the remaining balance of the contract was approximately $151 million. On May 19, 2021 we notified our original EPC firm that we were terminating the EPC Agreement, effective immediately. The cumulative billing on the EPC contract through June 30, 2021 was $63.2 million. The two major subcontracts for the Bakersfield Biorefinery were not terminated and were subsumed in the new replacement EPC agreement (see below). Accordingly, the two major subcontractors will continue to provide their services for the Bakersfield Biorefinery. On May 18, 2021 our BKRF subsidiary and CTCI Americas, Inc., a Texas corporation (“CTCI”), entered into a Turnkey Agreement with a Guaranteed Maximum Price for the Engineering, Procurement and Construction of the Bakersfield Renewable Fuels Project (the “CTCI EPC Agreement”). CTCI Americas is a worldwide leading provider of reliable engineering, procurement and construction services, including for the refinery market. Under the CTCI EPC Agreement, CTCI has agreed to provide services to complete the engineering, procurement, construction, pre-commissioning, commissioning, start-up and testing of our renewable diesel production facility under construction in Bakersfield, California. CTCI’s fees and costs, including direct costs, overhead fees and the contractor’s fee, are guaranteed not to exceed $178 million (which maximum price is subject to adjustment for certain change orders). The obligations of CTCI have been guaranteed by CTCI Corporation, the Taiwanese parent company of CTCI Environmental Remediation Liabilities The Company recognizes its asset retirement obligation and environmental remediation liabilities and has estimated such liabilities as of its acquisition date. It is the Company’s policy to accrue environmental and clean-up related costs of a non-capital nature when it is both probable that a liability has been incurred and the amount can be reasonably estimated. Environmental remediation liabilities represent the current estimated costs to investigate and remediate contamination at our properties. This estimate is based on internal and third-party assessments of the extent of the contamination, the selected remediation technology and review of applicable environmental regulations, typically considering estimated activities and costs for 20 years, and up to 30 years if a longer period is believed reasonably necessary. Accruals for estimated costs from environmental remediation obligations generally are recognized no later than completion of the remedial feasibility study and include, but are not limited to, costs to perform remedial actions and costs of machinery and equipment that are dedicated to the remedial actions and that do not have an alternative use. Such accruals are adjusted as further information develops or circumstances change. We discount environmental remediation liabilities to their present value if payments are fixed and determinable. However, as the timing and amount of these costs were undeterminable as of September 30, 2021, these costs have not been discounted. Expenditures for equipment necessary for environmental issues relating to ongoing operations are capitalized. Changes in laws and regulations and actual remediation expenses compared to historical experience could significantly impact our results of operations and financial position. We believe the estimates selected, in each instance, represent our best estimate of future outcomes, but the actual outcomes could differ from the estimates selected. At September 30 2021, accrued environmental remediation liability costs totaled $21.0 million of which $1.5 million have been classified as current liabilities. At December 31, 2020, accrued environmental liabilities totaled $21.3 million of which $0.9 million have been classified as current liabilities. On May 7, 2020 through BKRF OCB, LLC, one of the Company’s indirect subsidiaries, the Company purchased all of the outstanding equity interests of Bakersfield Renewable Fuels, LLC from Alon Paramount for a total consideration of $89.4 million, including $40 million in cash and assumption of liabilities of $43.9 million. Bakersfield Renewable Fuels, LLC owns an oil refinery in Bakersfield, California that the Company is retooling into a biorefinery. In connection with the acquisition, BKRF OCB, LLC agreed to undertake certain cleanup activities at the refinery and provide a guarantee for liabilities arising from the cleanup. The Company has assumed significant environmental and clean-up liabilities associated with the purchase of the Bakersfield Refinery. Leases On May 1, 2019, the Company amended its Torrance, California office lease to extend the lease term to July 31, 2022. On January 1, 2021, the Company entered into a lease agreement for a storage facility in Montana. The storage facility will be used for SusOils operations and runs through December 31, 2022. On April 20, 2021, the Company entered into a 36 month lease agreement for two Zephir electric railcar movers for use at the Bakersfield Biorefinery. The table below represents the amounts due through the end of lease terms.
On April 20, 2021, BKRF entered into a three-year lease beginning upon delivery of two railcar movers. The equipment was delivered in August and the first monthly payment was made in September 2021. The monthly payment is $13,551 and has an interest rate of 3%. On September 24, 2021, SusOils entered into a five-year lease beginning on November 1, 2021 for its North American headquarters, a new state-of-the-art facility located in Great Falls, Montana. This new facility will consolidate SusOils crop innovation programs, commercial grower support and executive and administrative activities at one location and will be fully operational by November 1, 2021 . Under the lease, we will have to pay monthly rental payments of $18,531. .
Legal BKRF, formerly Alon Bakersfield Property, Inc., is one of the parties to an action pending in the United States Court of Appeals for the Ninth Circuit. In June 2019, the jury awarded the plaintiffs approximately $6.7 million against Alon Bakersfield Property, Inc. and Paramount Petroleum Corporation (a parent company of Alon Bakersfield Property, Inc. at the time of the award in 2019). Under the agreements pursuant to which we purchased BKRF, In August, 2020, Wood Warren & Co. Securities, LLC (“Wood Warren”) filed a complaint in the Superior Court of California, Wood Warren & Co Securities, LLC vs. GCE Holdings Acquisitions, LLC , CaseIn December, 2020, Roll Energy Investments LLC (“Roll”) filed a complaint in the Superior Court of California, Los Angeles County, titled Roll Energy Investments LLC v. Global Clean Energy Holdings, Inc., Case No. 20RTCV00921. Roll alleged that the Company breached a promissory note in the principal sum of $0.3 million. Roll sought $0.4 million for principal and interest as of December 4, 2020, plus prejudgment interest allegedly accruing thereafter. On or about May 12, 2021, the company wired $0.5 million as full settlement of the amount due. On or about June 7, 2021, the Company and Roll entered into a Settlement Agreement to fully resolve Roll’s claims, accepting the amount previously wired with no additional amounts due. On or about June 29, 2021, Roll dismissed the action in its entirety, with prejudice.In the ordinary course of business, the Company may face various claims brought by third parties and the Company may, from time to time, make claims or take legal actions to assert the Company’s rights, including intellectual property rights, contractual disputes and other commercial disputes. Any of these claims could subject the Company to litigation. Management believes the outcomes of currently pending claims will not likely have a material effect on the Company’s consolidated financial position and results of operations. Indemnities and Guarantees In addition to the indemnification provisions contained in the Company’s organization documents, the Company generally enters into separate indemnification agreements with the Company’s directors and officers. These agreements require the Company, among other things, to indemnify the director or officer against specified expenses and liabilities, such as attorneys’ fees, judgments, fines and settlements, paid by the individual in connection with any action, suit or proceeding arising out of the individual’s status or service as the Company’s directors or officers, other than liabilities arising from willful misconduct or conduct that is knowingly fraudulent or deliberately dishonest, and to advance expenses incurred by the individual in connection with any proceeding against the individual with respect to which the individual may be entitled to indemnification by the Company. The Company also indemnifies its lessor in connection with its facility lease for certain claims arising from the use of the facility. These guarantees and indemnities do not provide for any limitation of the maximum potential future payments the Company could be obligated to make. Historically, the Company has not been obligated nor incurred any payments for these obligations and, therefore, no liabilities have been recorded for these indemnities and guarantees in the accompanying condensed consolidated balance sheets. COVID-19 In December 2019, a novel strain of coronavirus diseases (“COVID-19”) was first reported in Wuhan, China. Less than four months later, on March 11, 2020, the World Health Organization declared COVID-19 a global pandemic. The extent of COVID-19’s effect on the Company’s operational and financial performance is ongoing, but the Company believes that the pandemic to date has not materially impacted the Company’s operations and that the pandemic is not expected to be materially disruptive to its future plans and targeted date of beginning commercial operations, although certain supply chain disruptions could impact the completion date of the Bakersfield Biorefinery. The Company has implemented strict protocols on its on-site workforce and continues to monitor the potential impacts to its business. The extent of the impact of the COVID-19 pandemic on the Company’s operations, cash flows, liquidity and capital resources is highly uncertain, as information is evolving with respect to the duration and severity of the virus and its variants. However, based on its experience with the disease to date, the Company expects that the future impacts due to COVID-19 are not likely to be materially disruptive to its ongoing business. Acquisitions On July 20, 2021, the Company entered into a non-binding Letter of Intent to acquire an off-shore company that owns certain patents, feedstock pathway expertise and intellectual property related to camelina development. The consummation of the transaction is subject to the Company's completion of its due diligence review and the preparation of mutually acceptable transaction documents. The transaction is expected to close by November 30, 2021. |